Changes between Version 1 and Version 2 of 2023-6-15


Ignore:
Timestamp:
Jun 15, 2023, 8:02:24 PM (2 years ago)
Author:
Tom Goddard
Comment:

--

Legend:

Unmodified
Added
Removed
Modified
  • 2023-6-15

    v1 v2  
    1616= Discussion Notes =
    1717
     18* NIAID contract
     19  - Contract is finalized
     20  - 10 months, start May 1
     21  - Will produce May monthly progress report soon
    1822
     23* Plato operating system update
     24  - Expect OS upgrade to Rocky 8 to be complete in a few weeks.
     25  - Crick should be updated early next week.  CentOS 7 file-system still available on disk.
     26  - CGL primary and backup are at Rocky 9.1.
     27  - Scooter fixed LDAP, web tools, working on clustermaker web service
     28  - Selina does not yet have an account.  IT is handling 50 new account backlog.
    1929
     30* Power outage Wed June 21, midnight
     31  - Will affect N108 server room where switch we use is located.
     32
     33* Email filtering
     34  - We will tell UCSF IT we are ready to enable ProofPoint.
     35  - Expect some hiccups.
     36
     37* GPUs for Selina's machine learning
     38  - Our 4 A40 GPU node is here but not installed.
     39  - Other GPU nodes are at Oyster Point storage and cannot be moved because our server room has lots of equipment stacked up waiting to be installed.
     40
     41* Selina on machine learning
     42  - Described U-net, no-new-unet, and planned application to lung cancer tumor segmentation.
     43  - [https://docs.google.com/presentation/d/1Uabl7qpz77NN_av-_S3n94aHx8qW6tInW0MLwN06huA/edit#slide=id.p Slides]
     44  - [https://docs.google.com/document/d/1sdKY6jTOLdhRjBxKb9maMo7fKI-5rtCJJCSZEmxvlNE/edit Terminology]
     45  - [https://docs.google.com/document/d/1orr5Ym3wFndCG9g_2oBJH2bV_Ecp8JR4p-Jr_Ik6FSs/edit Articles]
    2046= Action Items =
    2147