| 19 | * NIAID contract renewal |
| 20 | - Scooter arranging time to talk to Darrell about NIAID contract. |
| 21 | - Last word is Darrell has worked out new prime contractor (not known who). |
| 22 | - Darrell is fully behind renewing our contract. |
| 23 | |
| 24 | * Hardware on order, UPS, tape backups |
| 25 | - New UPS (power supply) and tape backup hardware ordered in Sept and Oct still not delivered. |
| 26 | - Expected delivery in mid February. |
| 27 | |
| 28 | * R01 proposal revisions |
| 29 | - Went through progress section changes in Google Doc. |
| 30 | - References to reimplementing Chimera features removed. |
| 31 | - New AlphaFold progress section. |
| 32 | |
| 33 | * Next R01 revisions |
| 34 | - For next week's group meeting put research plan aims 1-3 text changes completed. |
| 35 | - Add time estimates in FTE to each of 6 sub aims totaling 2 FTE. |
| 36 | - Interactive MD for non-model building uses will be removed or minimized. |
| 37 | - DockPrep will be given stronger justification |
| 38 | - New machine learning structure prediction will mention prioritizing jobs. |
| 39 | |