wiki:2021-3-4

Attendees

  • Eric, TomG, Greg, Elaine, Scooter, TomF

Agenda

  • Action items
  • Funding
    • NTT Data - task order
    • R01 renewal, due July 5, 2021
    • U24 funding, this is what Cytoscape applied for
  • ChimeraX release date
  • Implications if Apple drops OpenGL sooner rather than latter
  • New hire job description
  • SPOKE

Discussion

  • SPOKE
    • new hire, full-time programmer
    • Discussion of SPOKE git issues mostly describing symptoms without solutions.
    • Scooter doing various fixes this week, out next week
  • NTT contract
    • Scooter put in NTT monthly report
  • CZI essential open source tools RFA.
    • Scooter suggests we propose developing web services
    • Move web services in Chimera paper to ChimeraX
  • New hire next steps
    • Scooter wrote up job description.
    • TomF says to open job requisition with HR
    • Scooter suggests TomG should plan to supervise work of new hire, and still be lead on projects new hire would take over from TomG.
  • Greg may have more time for ChimeraX
    • What tasks should he work on?
  • ChimeraX release
    • Main need is for R01 renewal.
    • Scooter suggests want strongest release for R01 renewal -- so can wait if needed to add important new features.
    • Eric working on color key gui, available next week
    • Greg wants soon release to get fixes to Toolshed bugs out
    • Scooter suggests early April release date

Action Items

  • Read last R01 specific aims and reviewer comments for next group meeting, Everyone
  • Buy Mac Mini with Apple Silicon and KVM switch, TomF
  • Figure out what additional plato directories need backup. Scooter
  • Try to setup 2-factor authentication for vpn, Scooter
  • Test new vpn on linux and document. Scooter
Last modified 5 years ago Last modified on Mar 4, 2021, 4:32:12 PM